Gallows Corner flyover to close overnight ahead of September full shutdown

The final resurfacing phase will see an overnight closure on 17 September and a weekend shutdown from 18 to 21 September, with reopening expected by end‑September.

News London evidence indexOpen analysis ▾
64/100Evidence
80/100Reporting
30/100Hype

Trust 64: council press release names Councillor Prince and provides dates, but lacks independent sources or documents.

Higher is stronger

Critic 80: explains impact, quotes official, gives specifics and next steps, but reads like a press release.

Higher is stronger

Hype 30: headline is dramatic but language remains proportionate to the council’s announcement.

Lower is better

ByNews London Desk
/London Edition/3 min read
ShareFacebookXWhatsApp
Gallows Corner flyover to close overnight ahead of September full shutdown

The Gallows Corner junction and its flyover will be fully closed overnight on Thursday 17 September and then experience a total shutdown from Friday night through to Monday morning. The closures are part of the last resurfacing stage that will restore the carriageways of the A127 and A12.

Schedule of closures

Read Next in News London3 min read
District line service cancelled between Edgware Road and Embankment on 24‑25 Oct 2026

District line service cancelled between Edgware Road and Embankment on 24‑25 Oct 2026

The shutdown also closes Fulham Broadway, Turnham Green and several tram routes, disrupting commuters and football fans across west London.

During the overnight shutdown on 17 September, traffic can still use the roundabout and access to the A12 eastbound, Straight Road and Main Road will remain open. From 10 pm on 18 September all vehicle movements through Gallows Corner will be prohibited, including routes to the A127 Southend Arterial Road, the A12 Colchester Road and the A118 Main Road. Diversion signs will guide drivers onto alternative routes for the three‑day period.

Work scope and contractors

Essex & Suffolk Water has finished its underground work, allowing Costain, the contractor appointed by Transport for London, to start the final reinstatement phase. Costain will lay new surfacing, apply white line markings and commission pedestrian crossings. The work will be carried out in sections to keep disruption to a minimum, but the full weekend closure is required to complete the resurfacing and related safety checks.

Related Borough Coverage4 min read
TfL asset backlog costs Londoners 830,000 hours in delays

TfL asset backlog costs Londoners 830,000 hours in delays

Commuters face significant delays due to £6.5 billion renewals backlog, with experts warning of further increases.

"The nightmare is almost over for residents and businesses who have had to put up with months of unacceptable disruption at Gallows Corner."

Councillor Keith Prince, Leader of Havering Council

Council’s next steps

Havering Council said it will continue to monitor the works and press TfL for business compensation. Councillor Keith Prince noted that he set an October deadline when he became leader and that the project now appears on track to finish before that date. The council urges motorists to plan journeys in advance and to avoid the area where possible during the final weeks of construction.

Questions this report answers

+When will the flyover be closed overnight?

The flyover will be fully closed from 10 pm on Thursday 17 September until 5 am on Friday 18 September. This short shutdown allows resurfacing work to begin before the full weekend closure.

+When does the complete closure of the junction take place?

A total shutdown of both the flyover and the roundabout starts at 10 pm on Friday 18 September and ends at 5 am on Monday 21 September. No vehicles will be able to pass through Gallows Corner during that time.

+When is the junction expected to reopen to normal traffic?

Havering Council confirmed that the junction and flyover should be fully reopened by the end of September 2026, which is ahead of the October deadline set by the council leader.

+What is the council doing for businesses affected by the disruption?

The council said it will keep pressing TfL for compensation on behalf of businesses that suffered loss during the prolonged diversions. It also urges residents and road users to use the provided diversion routes to reduce further impact.

News London Desk

This article was written at the News London news desk from the reporting of the outlets listed below it. Drafting is done by a language model under human editorial supervision — there is no reporter behind this byline, and we would rather say so than invent one.

How stories are produced and scoredWho runs News LondonCorrections

Daily edition

The London Ledger

A considered capital-wide edit delivered each morning.

More Coverage in Transport & TfL

District line service cancelled between Edgware Road and Embankment on 24‑25 Oct 2026
London

District line service cancelled between Edgware Road and Embankment on 24‑25 Oct 2026

3 min read
TfL asset backlog costs Londoners 830,000 hours in delays
London

TfL asset backlog costs Londoners 830,000 hours in delays

4 min read
TfL consults on all-electric minicab fleet by 2028
London

TfL consults on all-electric minicab fleet by 2028

3 min read
London bus and tram fares to rise by 10p from November 1
London

London bus and tram fares to rise by 10p from November 1

2 min read

Who else reported this

Our article above is written from the facts in these reports. Read the originals — every one is linked.

Capital conditions

Weather in central London

Loading live conditions…

Gallows Corner flyover closure | News London