HS2 tunnel reaches halfway to Euston, machines near West Hampstead advance
Karen and Madeleine have bored 2.25 miles of the 4.5‑mile route, moving roughly 16 metres each day and are scheduled to finish tunnelling in 2027.
News London evidence indexOpen analysis ▾
Multiple named officials, specific figures, dates and locations provide solid corroboration.
Higher is stronger
Offers context, quotes officials, precise data and next steps, though relies on press statements.
Higher is stronger
Measured language; no clickbait or exaggerated claims beyond quoted praise.
Lower is better
The HS2 tunnelling operation has reached the halfway point of its deep‑bored route to Euston, according to ianVisits. The two machines, named Karen and Madeleine, are now positioned between West Hampstead and Kilburn High Road stations. Their progress means that half of the planned 4.5‑mile underground corridor has been excavated, with work continuing around the clock.
How the tunnelling operation works
TfL to add up to 1,085 digital ad screens across London by 2028
The expansion will raise the total to about 3,733 screens, generating more than £170 million annually for the transport network
Each machine pushes forward roughly 16 metres each day, installing a precast concrete segment as it moves. The segments, totalling 48,294 for the Euston stretch, are manufactured in Hartlepool and shipped to the site. As the TBMs cut through chalk and London clay, they generate an estimated 1.5 million tonnes of spoil, which is loaded onto trains at Old Oak Common and dispatched for use in landscaping projects elsewhere, as reported by The Standard.
Reaching the halfway mark for building the programme’s last deep bored tunnel is a magnificent achievement by everyone involved.
Mark Wild, HS2 chief executive
IAG tells PM Heathrow third‑runway plan unaffordable, cites £19 billion gap
The airline group argues the scheme should cost £30 billion, not the £49 billion projected, and warns the current proposal cannot be funded without government help.
What happens after the boring stops
When the machines finish the final stretch, workers will dismantle most of the TBM bodies and pull them back through the completed tunnels. The 8.53‑metre‑wide cutterheads will stay in place until the large Euston cavern is built, after which they will be extracted for disposal, as explained by ianVisits. The steel shields at the front of the machines will remain as part of the tunnel lining, meaning future HS2 trains will travel through a section of the original boring equipment.
Local impact
Residents near West Hampstead have reported occasional vibration during the 24‑hour drilling cycle, but the Skanska Costain STRABAG joint venture says monitoring is continuous and complies with London’s noise and vibration standards. The presence of the steel shields will not affect the structural integrity of the tunnel, and the finished line is expected to improve connectivity for the surrounding boroughs once operational.
Next milestones and timeline
The tunnelling teams aim to complete the boring phase in 2027, after which the focus will shift to constructing the Euston cavern and fitting out the station. High‑speed services from Old Oak Common to Birmingham are slated for 2036‑39, while the Birmingham‑to‑Euston leg is projected for 2040‑43, according to The Standard. Rail Minister Lord Hendy said the progress demonstrates momentum toward delivering a railway that adds capacity and faster journeys for London, as reported by The Standard.
Questions this report answers
+How much tunnel has been bored so far?
The two tunnel boring machines have excavated 2.25 miles of the 4.5‑mile route, which represents half of the planned underground distance between Old Oak Common and Euston, as reported by ianVisits.
+When will the tunnelling be completed?
The tunnelling operation is expected to finish in 2027, with the machines stopping near the Euston approach before the cavern is built, according to information from ianVisits and The Standard.
+What will happen to the cutting heads after the tunnel is finished?
The 8.53‑metre‑wide cutterheads will remain buried until the Euston cavern is constructed; once that structure is in place, the heads will be removed for disposal, as explained by ianVisits.
News London Desk
This article was written at the News London news desk from the reporting of the outlets listed below it. Drafting is done by a language model under human editorial supervision — there is no reporter behind this byline, and we would rather say so than invent one.
How stories are produced and scoredWho runs News LondonCorrections
The London Ledger
A considered capital-wide edit delivered each morning.