/Property & Planning/ Lewisham//6 min read

Lewisham Hospital heat pump test risks River Ravensbourne sediment discharge

£18m NHS project drills boreholes in Ladywell Fields to assess open-loop system viability by 31 July

News London evidence indexOpen analysis ▾
52/100Evidence
85/100Reporting
35/100Hype

Trust score 52 due to specific figures and bodies cited but lacking named sources or documents.

Higher is stronger

Critic score 85 for clear relevance, specific data, next steps, but lacking direct quotes from individuals.

Higher is stronger

Hype score 35; language is mildly emphatic but not overly sensationalised.

Lower is better

ByNews London Desk
/London Edition/6 min read
ShareFacebookXWhatsApp
Lewisham Hospital heat pump test risks River Ravensbourne sediment discharge

Lewisham and Greenwich NHS Trust has begun testing an open-loop ground source heat pump system beneath Ladywell Fields, with boreholes drilled to assess the viability of extracting heat from the chalk aquifer. The project, costing £25m, has received £18m from the Department of Energy Security and Net Zero. If successful, it will replace the hospital’s 1970s gas boilers with a low-carbon heating system.

The test phase is being conducted under an Environment Agency permit that allows the discharge of water from drilling into the River Ravensbourne. However, the trust confirmed to Salamander News that water was also taken from the river to flush sediment from the boreholes, an action not covered by the permit. The volume of water extracted remains unclear.

Read Next in News London5 min read
Lewisham Library reopening delayed to late 2027 after structural flaws found

Lewisham Library reopening delayed to late 2027 after structural flaws found

Council blames unexpected brickwork issues around the building’s concrete core for the latest setback

Sediment discharge and river stress

During initial drilling, chalk sediment was discharged into the Ravensbourne, prompting concerns from local river protection groups. The trust stated that settlement tanks are now in use to prevent further sediment release. An Environment Agency representative has been assigned to monitor discharges, though details of the monitoring process have not been disclosed.

The River Ravensbourne is already under ecological stress. Thames Water and the Environment Agency are investigating a recent pollution incident in the River Pool, a tributary, which caused mass fish and eel deaths. The trust’s project coincides with a period of low water levels and elevated temperatures due to summer heatwaves.

Related Borough Coverage6 min read
Right to Buy in London: the discount is £16,000, not £136,400

Right to Buy in London: the discount is £16,000, not £136,400

The London cap fell by around £120,000 in November 2024. Most of what is published still quotes the old figure.

Test phase and long-term risks

The test involves two pairs of boreholes: a 90-metre abstraction well and a 10-metre monitoring well. Water will be pumped between them to assess flow rates and potential impacts on the aquifer. The trust expects to complete its analysis by 31 July, though it is unclear how short-term tests will predict long-term effects on groundwater levels and temperature.

If approved, the full project will require six additional borehole pairs, a monitoring borehole, and a 1-metre trench for pipes and cables. The system could later be adapted for cooling, but the Environment Agency classified heat as a groundwater pollutant in 2023, raising regulatory concerns for such modifications.

We're all for action on climate change and decarbonising our public services, but not at the expense of our rivers and green spaces. Our waters are already under immense stress, and this project risks adding to that pressure without proper safeguards.

Paul de Zylva, Chair, Quaggy Waterways Action Group

Ecological surveys and transparency concerns

The trust conducted an arboriculture survey, which led to the relocation of abstraction boreholes closer to a children’s playground. However, an ecological survey reviewed by Salamander News was limited to a species list for the park and did not assess long-term impacts on groundwater, soils, or river ecosystems.

A hydrogeological survey, which could address risks such as thermal plumes altering groundwater temperature, remains confidential. The trust cited commercial sensitivity for withholding the document. Open-loop systems, which account for fewer than one in every 100 ground source heat pumps installed, are considered higher risk due to their potential impact on aquifers.

What happens next

The trust will finalise test results by 31 July. If the project proceeds, construction of the full system could begin later this year. Residents and river protection groups have called for greater transparency, including public access to ecological and hydrogeological assessments. The Environment Agency will continue to monitor discharges during the test phase.

Questions this report answers

+How much funding has the Lewisham Hospital heat pump project received?

The project has received £18m from the Department of Energy Security and Net Zero. The total cost is £25m. This funding will cover the installation of an open-loop ground source heat pump system beneath Ladywell Fields.

+What are the risks to the River Ravensbourne from this project?

The project has already discharged chalk sediment into the river during drilling. The Environment Agency permit allows water release, but unpermitted water extraction for flushing boreholes has raised concerns about ecological stress on the already fragile river system.

+When will the test results for the heat pump project be known?

Lewisham and Greenwich NHS Trust expects to understand the test results by 31 July. These results will determine whether the full project, involving six more borehole pairs, proceeds.

+Why are local groups concerned about the heat pump system?

Local river action groups, such as Quaggy Waterways Action Group, are concerned about long-term impacts on the aquifer and river ecology. The Environment Agency recognises heat as a groundwater pollutant, and open-loop systems are considered higher risk due to potential thermal plumes and sediment discharge.

News London Desk

This article was written at the News London news desk from the reporting of the outlets listed below it. Drafting is done by a language model under human editorial supervision — there is no reporter behind this byline, and we would rather say so than invent one.

How stories are produced and scoredWho runs News LondonCorrections

Daily edition

The London Ledger

A considered capital-wide edit delivered each morning.

More Coverage in Property & Planning

Lewisham Library reopening delayed to late 2027 after structural flaws found
Lewisham

Lewisham Library reopening delayed to late 2027 after structural flaws found

5 min read
Right to Buy in London: the discount is £16,000, not £136,400
London

Right to Buy in London: the discount is £16,000, not £136,400

6 min read
Section 21 has gone. What that changes for renters in London
London

Section 21 has gone. What that changes for renters in London

8 min read
Bromley homes face five top-10 risks as buyers spend £6.5bn despite warnings
London

Bromley homes face five top-10 risks as buyers spend £6.5bn despite warnings

5 min read

Who else reported this

Our article above is written from the facts in these reports. Read the originals — every one is linked.